Week of 5/11/20 - 5/15/20

This week the Marchese crew will continue to finish pouring the remaining sections of the concrete sidewalks from Pond St to Federal St. The new bump out at Pond St will be constructed and concrete poured. They will also be working on grading and prep for the new sidewalks in the stretch from Federal St to Bow St.

Read More
Week of 4/27/20 - 5/1/20

The Marchese crew continues to pour sections of the concrete sidewalks from Pond St up to the bump out across from the church. During the rainy conditions the crew started and will continue to demolish the old sidewalks in the stretch from Federal St to Bow St.

Read More
Phase 2Sean Ciancarelli
Week of 4/20/20 - 4/24/20

Most of all the curbing has been installed between Pond St and Federal St including the bump out across the street from St. Mary’s Church. The Marchese crew has started to pour the concrete sidewalks from Pond St up to the bump out across from the church.

Read More
Phase 2Sean Ciancarelli
Week of 3/30/20 - 4/10/20

Week of March 30th - April 3rd - City crews will begin to install electrical conduit on the even side on the road between Pond St to Federal St. Trees and parking kiosks will be taken down. Sidewalk contractor may begin to jackhammer in front of the curb line and start to demo the sidewalks.

Read More