Week of 4/20/20 - 4/24/20
Most of all the curbing has been installed between Pond St and Federal St including the bump out across the street from St. Mary’s Church. The Marchese crew has started to pour the concrete sidewalks from Pond St up to the bump out across from the church. They will continue pour the sidewalks in this area and finish landscaping details in this area. Depending on weather conditions (rain) the Marchese crew could begin demo of the sidewalks in the stretch from Federal St to Bow St. Verizon shifted one of their manholes that was directly in the middle of the City’s new curb line. City of Beverly DPS crews continue to install the electrical conduit for the new street lighting, tree pits, electrical hand holes, street light bases, street lights and add drainage infrastructure.