N Granese is working on completing their construction in the Phase 2 area. After Wednesday (11/13) the water bypass should be removed except for the area between Thorndike St and Vestry St.
Read MoreN Granese has completed the first phase of water main lining work from Pickett St to St. Mary’s Church. They are currently on the final reinstallations of water services for residents and businesses in that phase. They have started the next phase (St. Mary’s to Railroad Ave) by laying the temporary water main on the side of the road.
Read MoreN Granese has completed the first phase of water main lining work from Pickett St to St. Mary’s Church. They are currently reinstalling water services for residents and businesses in that phase.
Read MoreN Granese is currently cleaning and lining the water main with two separate crews between Lenox St and Elliott St. The next phase of the project will be between Elliott St and St. Mary’s.
Read MoreNEUCO (National Grid Gas subcontractor) has completed their work within the project limits.
Read MoreNEUCO (National Grid Gas subcontractor) will continue installing services to the buildings this week. The crew will also be preforming a couple old main cutoffs. NEUCO plans to be done with the project this week.
Read MoreNEUCO (National Grid Gas subcontractor) will continue installing the new plastic gas main this week. One crew will continue installing main On Church Street and then move to Winter Street. The second crew will be installing gas services to the businesses within the project limits.