Week of 11/18/19 - 11/22/19
N Granese is working on completing their construction in the Phase 1/2 area. They will be finished their work on Friday November 22nd. A link to that project can be found here.
The sidewalk contractor (J Marchese) is finishing up construction on the odd side of the road and will be finished by Wednesday November 27th. The contractor will reconstruct the even side of the road starting in the Spring of 2020. The road will also be reclaimed and paved next year as well.
Expect delays and proceed with caution. The City of Beverly puts a high priority on the safety of the construction workers and police officers. Let ‘em work! Let ‘em live!