Week of 3/18/19 - 3/22/19

NEUCO (National Grid Gas subcontractor) finished digging test pits last Friday.

They will start saw cutting their new gas main corridor on Monday. Installation of the main will begin on Tuesday and continue through Friday. Main installation will start at Pond Street and work towards Federal Street.  

Expect delays and proceed with caution. The safety of the construction workers and policemen is most important.