Cabot Street Project

View Original

Week of 4/27/20 - 5/1/20

The Marchese crew continues to pour sections of the concrete sidewalks from Pond St up to the bump out across from the church. During the rainy conditions the crew started and will continue to demolish the old sidewalks in the stretch from Federal St to Bow St.

Boston Welding (National Grid electric sub contractor) has started the process of fixing their electrical vaults/vents to meet our new sidewalk elevation.

City of Beverly DPS crews continue to install the electrical conduit for the new street lighting, tree pits, electrical hand holes, street light bases, street lights and add drainage infrastructure. They are currently working in the section between Federal and Bow Street.